Claim

0

The Elevated Evacuated Tube can be designed so that lift-fan power-loss will not endanger people or infrastructure below.

Evidence

Although the Elevated Evacuated Tube would be designed with substantial redundancy in its terrestrial power generation, transmission, distribution, and lift-control systems, complete or partial loss of lift-fan power cannot be treated as impossible. Power interruption could result from deliberate sabotage, aircraft collision, wildfire, earthquake, lightning damage, cyberattack, cascading grid failure, control-system malfunction, manufacturing defect, maintenance error, or an unanticipated design flaw. Even if these events are made unlikely, the consequences of lift-fan power loss must be considered explicitly.

The central safety objective is not merely to keep the EET aloft under normal conditions. The system must also be designed so that, in the unlikely event of major power loss, the EET does not create an unacceptable risk to people, vehicles, or critical infrastructure below it.

The first mitigation is siting. Where practical, the EET should be routed over sparsely occupied land, water, industrial corridors, or other areas with limited fragile infrastructure. The preferred route should avoid schools, hospitals, retirement homes, dense housing, emergency-services facilities, high-voltage substations, fuel depots, and other sensitive or high-consequence sites.

The second mitigation is land-use control beneath the EET. The region below the tube can be treated as a low-human-risk safety corridor, similar in concept to a green belt, utility corridor, airport runway protection zone, or railroad right-of-way. Sensitive uses can be excluded or relocated. Existing structures within the corridor can be evaluated and, where appropriate, upgraded to withstand loads comparable to hurricane-force winds, heavy snow accumulation, or localized debris impact. Some fragile infrastructure, such as antennas, light poles, overhead power lines, or wind turbines, may need to be relocated, hardened, or treated as sacrificial infrastructure.

The third mitigation is operational exclusion during launch windows. Roads, parks, sports fields, trails, golf courses, and other public-use areas within the safety corridor can be temporarily closed during launch operations. Road crossings can use warning lights, gates, and stop signals comparable to railway crossings. Emergency signs and automated alerts can instruct drivers and pedestrians to leave the safety corridor immediately if a lift-power anomaly is detected. These measures reduce the probability that people are present below the EET during the period when consequence management matters most.

The fourth mitigation is controlled descent. The EET should not be treated as a passive object that simply falls if external power is interrupted. Distributed emergency batteries, supercapacitors, flywheels, or other reserve power systems can provide enough short-duration energy for attitude control, guidance, valve actuation, parachute deployment, and final descent-rate reduction. This reserve power need not keep the entire EET airborne indefinitely. Its purpose is to convert an uncontrolled fall into a guided emergency descent into the safety corridor.

A useful analogy is autorotation in a helicopter, where stored aerodynamic and rotational energy can be used to reduce descent speed near the ground. The EET equivalent would not need to reproduce helicopter autorotation exactly. Rather, the design objective would be similar: preserve enough emergency control authority to keep the structure aligned, prevent tumbling, avoid drifting outside the safety corridor, and reduce vertical speed before ground contact.

The EET can also be designed to land onto prepared capture infrastructure. For example, wires, nets, catenary cables, crushable supports, or energy-absorbing frames could be installed along the safety corridor. These systems could be designed to keep the tube shell and lift-fan rotors from striking the ground directly. In the preferred failure mode, the EET would settle onto this prepared capture system rather than impacting roads, buildings, or terrain.

A hard uncontrolled fall is also less severe than it may initially appear because the EET is a very lightweight, high-drag structure. The EET supported altitude claim estimates a total structural and lift-system mass of roughly 436 kg per meter and an external radius of approximately 3.3 m, giving a broadside projected area of about 6.6 m² per meter of tube. Using a simple broadside-drag estimate,

vt=2mgρCdAv_t = \sqrt{\frac{2mg}{\rho C_d A}}

and assuming m=436m = 436 kg/m, A=6.6A = 6.6 m²/m, Cd1.2C_d \approx 1.2, and near-sea-level air density ρ=1.225\rho = 1.225 kg/m³, the near-ground terminal velocity is approximately 30 m/s, or about 67 mph. At higher altitude, where air density is lower, the local terminal velocity will be slightly higher.

Parachutes or ballutes (inflatable drag devices) can reduce this speed further. For example, reducing the near-ground descent speed to roughly 15 m/s would require total effective drag area of about 31 m² per meter of tube, compared with roughly 8 m² per meter from the bare broadside tube alone. Reducing it to roughly 10 m/s would require about 70 m² of effective drag area per meter. These are not final design values, but they show that the relevant safety question is one of distributed drag-area design, not uncontrolled ballistic impact.

Airbags on the underside of the EET can be deployed to soften impact.

The EET should also include venting provisions. Because the tube is evacuated during normal operation, valves or rupture panels can be opened during an emergency descent to admit air in a controlled way. This would reduce pressure-differential loads, prevent implosion during impact or capture, and make the structure less hazardous after landing.

The most credible worst case is therefore not that the EET crashes like a dense aircraft or launch vehicle. It is that a very long, lightweight, high-drag structure descends into a prepared safety corridor, possibly causing localized damage to trees, antennas, utility poles, fences, signs, traffic lights, power lines, or fragile industrial equipment. Those consequences are serious and must be engineered for, but they are not automatically catastrophic.

Accordingly, lift-fan power loss should be treated as a required safety case for the EET rather than as a disqualifying failure mode. Through route selection, exclusion zoning, launch-window closures, emergency traffic control, reserve descent power, aerodynamic braking, venting, and prepared capture infrastructure, the EET can be designed so that even severe lift-power failures do not create an unacceptable risk of death or major infrastructure loss below the tube.

Reviews

The following reviews are limited in scope to the validity of the claim made above, and do not imply that the reviewer has taken a position regarding any other claim or the overall feasibility of a concept that is supported by this claim.

No reviews yet.